Dept. of Trans. PROGRESS Serial No. Contract No. 16-050-13-55 11-406904 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 4% Location: Federal Project: 11-SD-8-R25.9/R32.2 STPI-008-1(314) Progress payment No. 012 Payment period ending: 02-20-16 DALEY CORP 12570 HWY 67 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,478,095.89 193,445.50 2. a. Extra Work 148,685.00 6,601.78 b. Adustment Comp. -747,903.30 0.00 3. Materials on Hand 30,953.34 -25,903.18 4. Earned Subject to Retention 7,909,830.93 174,144.10 5. Mobilization 288,325.00 0.00 6. Total Work Completed 8,167,202.59 7. Deductions -3,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,195,155.93 172,144.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 172,144.10