Dept. of Trans. PROGRESS Serial No. Contract No. 16-203-15-29 11-406904 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 88% Location: Federal Project: 11-SD-8-R25.9/R32.2 STPI-008-1(314) Progress payment No. 018 Payment period ending: 07-20-16 DALEY CORP 12570-10 HWY 67 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,690,712.33 132,143.84 2. a. Extra Work 576,340.84 18,063.52 b. Adustment Comp. -714,342.30 33,561.00 3. Materials on Hand 0.00 -24,930.18 4. Earned Subject to Retention 8,552,710.87 158,838.18 5. Mobilization 288,325.00 0.00 6. Total Work Completed 8,841,035.87 7. Deductions -125,000.00 -125,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,716,035.87 33,838.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,838.18