Dept. of Trans. PROGRESS Serial No. Contract No. 16-235-17-37 11-406904 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 65% Location: Federal Project: 11-SD-8-R25.9/R32.2 STPI-008-1(314) Progress payment No. 019 Payment period ending: 08-20-16 DALEY CORP 12570-10 HWY 67 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,707,341.93 16,629.60 2. a. Extra Work 641,830.13 65,489.29 b. Adustment Comp. -714,342.30 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,634,829.76 82,118.89 5. Mobilization 288,325.00 0.00 6. Total Work Completed 8,923,154.76 7. Deductions -2,000.00 123,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,921,154.76 205,118.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,118.89