Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-076-08-34 11-406904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-8-R25.9/R32.2 STPI-008-1(314) Progress payment No. 022 Payment period ending: 11-04-16 DALEY CORP 12570-10 HWY 67 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,717,080.47 0.00 2. a. Extra Work 666,262.83 0.00 b. Adustment Comp. -775,297.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,608,045.72 0.00 5. Mobilization 288,325.00 0.00 6. Total Work Completed 8,896,370.72 7. Deductions -1,470.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,894,900.72 20,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,000.00