Dept. of Trans. PROGRESS Serial No. Contract No. 16-299-10-55 11-407004 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 70% Location: Federal Project: 11-SD-8-R61.2/R77.8 NHPI-008-1(315) Progress payment No. 015 Payment period ending: 10-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,082,199.77 3,741,736.33 2. a. Extra Work 91,680.61 32,458.60 b. Adustment Comp. -875,677.33 -9,067.30 3. Materials on Hand 4. Earned Subject to Retention 19,298,203.05 3,765,127.63 5. Mobilization 3,479,142.20 173,957.11 6. Total Work Completed 22,777,345.25 7. Deductions -1,576,500.00 -365,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,200,845.25 3,573,584.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,573,584.74