Dept. of Trans. PROGRESS Serial No. Contract No. 16-327-16-28 11-407004 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 100% Location: Federal Project: 11-SD-8-R61.2/R77.8 NHPI-008-1(315) Progress payment No. 016 Payment period ending: 11-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,156,855.19 4,074,655.42 2. a. Extra Work 91,680.61 0.00 b. Adustment Comp. -1,376,680.87 -501,003.54 3. Materials on Hand 4. Earned Subject to Retention 22,871,854.93 3,573,651.88 5. Mobilization 3,479,142.20 0.00 6. Total Work Completed 26,350,997.13 7. Deductions -1,880,000.00 -303,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions -357,365.19 -357,365.19 c. Reduction after 95% Comp. 9. Total pay to Contractor 24,113,631.94 2,912,786.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,912,786.69