Dept. of Trans. PROGRESS Serial No. Contract No. 16-358-09-51 11-407004 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 11-SD-8-R61.2/R77.8 NHPI-008-1(315) Progress payment No. 017 Payment period ending: 12-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,024,076.98 1,867,221.79 2. a. Extra Work 120,730.79 29,050.18 b. Adustment Comp. -1,338,510.04 38,170.83 3. Materials on Hand 4. Earned Subject to Retention 24,806,297.73 1,934,442.80 5. Mobilization 3,479,142.20 0.00 6. Total Work Completed 28,285,439.93 7. Deductions -2,137,500.00 -257,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 357,365.19 c. Reduction after 95% Comp. 9. Total pay to Contractor 26,147,939.93 2,034,307.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,034,307.99