Dept. of Trans. PROGRESS Serial No. Contract No. 17-025-13-49 11-407004 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 11-SD-8-R61.2/R77.8 NHPI-008-1(315) Progress payment No. 018 Payment period ending: 01-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,846,463.15 822,386.17 2. a. Extra Work 120,730.79 0.00 b. Adustment Comp. -1,222,567.95 115,942.09 3. Materials on Hand 4. Earned Subject to Retention 25,744,625.99 938,328.26 5. Mobilization 3,479,142.20 0.00 6. Total Work Completed 29,223,768.19 7. Deductions -2,458,500.00 -321,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,765,268.19 617,328.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 617,328.26