Dept. of Trans. PROGRESS Serial No. Contract No. 17-054-09-15 11-407004 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 11-SD-8-R61.2/R77.8 NHPI-008-1(315) Progress payment No. 019 Payment period ending: 02-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,942,277.93 1,095,814.78 2. a. Extra Work 120,730.79 0.00 b. Adustment Comp. -1,222,567.95 0.00 3. Materials on Hand 4. Earned Subject to Retention 26,840,440.77 1,095,814.78 5. Mobilization 3,479,142.20 0.00 6. Total Work Completed 30,319,582.97 7. Deductions -2,456,500.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,863,082.97 1,097,814.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,097,814.78