Dept. of Trans. PROGRESS Serial No. Contract No. 17-115-15-42 11-407004 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 11-SD-8-R61.2/R77.8 NHPI-008-1(315) Progress payment No. 021 Payment period ending: 04-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,420,343.56 84,532.43 2. a. Extra Work 589,746.12 326,899.02 b. Adustment Comp. -1,217,679.89 0.00 3. Materials on Hand 4. Earned Subject to Retention 27,792,409.79 411,431.45 5. Mobilization 3,479,142.20 0.00 6. Total Work Completed 31,271,551.99 7. Deductions -36,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,235,551.99 406,431.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 406,431.45