Dept. of Trans. PROGRESS Serial No. Contract No. 16-112-16-08 11-407604 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 43% Location: Federal Project: 11-SD-5-0.0 HSNH-PX07-3(112) Progress payment No. 005 Payment period ending: 04-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,282,870.78 357,218.70 2. a. Extra Work 14,960.79 14,960.79 b. Adustment Comp. 3. Materials on Hand 0.00 -61,240.90 4. Earned Subject to Retention 1,297,831.57 310,938.59 5. Mobilization 118,000.00 5,900.00 6. Total Work Completed 1,415,831.57 7. Deductions -2,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,413,831.57 315,838.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 315,838.59