Dept. of Trans. PROGRESS Serial No. Contract No. 16-144-14-22 11-408004 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 58% Location: Federal Project: 11-SD-79-0.0/29.6 STP-P079(38) Progress payment No. 002 Payment period ending: 05-20-16 PAL GENERAL ENGINEERING INC 5374 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 122,313.10 68,950.68 2. a. Extra Work 1,721.14 1,721.14 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 124,034.24 70,671.82 5. Mobilization 45,750.00 15,250.00 6. Total Work Completed 169,784.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 169,784.24 85,921.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,921.82