Dept. of Trans. PROGRESS Serial No. Contract No. 16-235-17-50 11-408004 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 91% Location: Federal Project: 11-SD-79-0.0/29.6 STP-P079(38) Progress payment No. 005 Payment period ending: 08-20-16 PAL GENERAL ENGINEERING INC 5374 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,715.23 159,830.56 2. a. Extra Work 29,757.91 16,400.63 b. Adustment Comp. 3. Materials on Hand 163,787.74 -14,334.04 4. Earned Subject to Retention 815,260.88 161,897.15 5. Mobilization 61,000.00 0.00 6. Total Work Completed 712,473.14 7. Deductions -15,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 861,260.88 151,897.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,897.15