Dept. of Trans. PROGRESS Serial No. Contract No. 16-358-07-47 11-409804 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 17% Location: Federal Project: 11-SD-78-1.5/12.2 NHP-P078(116) Progress payment No. 003 Payment period ending: 12-20-16 PAL GENERAL ENGINEERING INC 5374 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 165,126.83 148,587.13 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 165,126.83 148,587.13 5. Mobilization 44,835.00 44,835.00 6. Total Work Completed 209,961.83 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 208,961.83 193,422.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,422.13