Dept. of Trans. PROGRESS Serial No. Contract No. 21-202-18-25 11-410404 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 79% Location: Federal Project: 11-IMP-8-R36.5/R37.5 ACIM-008-2(111) Progress payment No. 016 Payment period ending: 07-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,231,057.41 1,242,491.03 2. a. Extra Work 106,542.53 7,678.76 b. Adustment Comp. 3. Materials on Hand 487,142.34 -23,633.60 4. Earned Subject to Retention 14,824,742.28 1,226,536.19 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 16,737,599.94 7. Deductions -4,940.00 -4,130.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,219,802.28 1,222,406.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,222,406.19