Dept. of Trans. PROGRESS Serial No. Contract No. 15-352-17-44 11-410604 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 30% Location: Federal Project: 11-SD-5-R1.2 STP-000C(402) Progress payment No. 002 Payment period ending: 12-20-15 WESTERN RIM CONSTRUCTORS, INC. 912 S ANDREASEN DRIVE, STE108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 189,758.68 165,083.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 189,758.68 165,083.10 5. Mobilization 158,854.43 158,854.43 6. Total Work Completed 348,613.11 7. Deductions -58,928.81 -57,928.81 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 289,684.30 266,008.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,008.72