Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-16-16 11-410604 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 41% Location: Federal Project: 11-SD-5-R1.2 STP-000C(402) Progress payment No. 003 Payment period ending: 01-20-16 WESTERN RIM CONSTRUCTORS, INC. 912 S ANDREASEN DRIVE, STE108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 265,351.50 75,592.82 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 265,351.50 75,592.82 5. Mobilization 201,215.61 42,361.18 6. Total Work Completed 466,567.11 7. Deductions -74,109.82 -15,181.01 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 392,457.29 102,772.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,772.99