Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-13-32 11-410704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 94% 11-IMP-8-80.5/80.9 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-13 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 583,633.15 50,292.00 2.a. Extra Work 7,016.80 7,016.80 b. Adjustment Comp. -226.37 -226.37 3. Materials on Hand 4. Earned Subject to Retention 590,423.58 57,082.43 5. Mobilization 68,000.00 0.00 6. Total Work Completed 658,423.58 7. Deductions -9,859.38 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 648,564.20 54,082.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,082.43