Dept. of Trans. PROGRESS Serial No. Contract No. 18-053-07-45 11-410804 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 27% Location: Federal Project: 11-SD-805-15.7/17.5 ACIM-805-1(637) Progress payment No. 004 Payment period ending: 02-20-18 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 488,685.31 164,722.23 2. a. Extra Work 1,315.16 1,315.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 490,000.47 166,037.39 5. Mobilization 226,361.25 47,655.00 6. Total Work Completed 716,361.72 7. Deductions -5,965.77 -203.32 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 710,395.95 213,489.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 213,489.07