Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 19-247-13-30 11-411104 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 67% Location: Federal Project: 11-SD-94-7.2/10.5 ACNH-X073(130) Progress payment No. 011 Payment period ending: 08-20-19 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,342,248.94 0.00 2. a. Extra Work 197,659.76 67,275.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,539,908.70 67,275.00 5. Mobilization 280,000.00 0.00 6. Total Work Completed 2,819,908.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,819,908.70 67,275.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,275.00