Dept. of Trans. PROGRESS Serial No. Contract No. 19-354-13-42 11-411344 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 34% Location: Federal Project: 11-SD-8-12.0/13.0 ACNH-X073(137) Progress payment No. 002 Payment period ending: 12-20-19 JAZZAR CONSTRUCTION GROUP INC 192 TECHNOLOGY DR #M IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 536,517.84 157,410.02 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 536,517.84 157,410.02 5. Mobilization 190,000.00 40,000.00 6. Total Work Completed 726,517.84 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 726,517.84 197,410.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,410.02