Dept. of Trans. PROGRESS Serial No. Contract No. 23-052-14-14 11-4114A4 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 6% Location: Federal Project: 11-SD-125-9.6/13.2 ACNH-P125(20) Progress payment No. 001 Payment period ending: 02-20-23 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,413.55 45,413.55 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 45,413.55 45,413.55 5. Mobilization 6. Total Work Completed 45,413.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 45,413.55 45,413.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,413.55