Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-113-11-04 11-4114A4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-125-9.6/13.2 ACNH-P125(20) Progress payment No. 022 Payment period ending: 12-09-24 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,662,157.76 14,810.00 2. a. Extra Work 546,291.85 8,649.72 b. Adustment Comp. 116,930.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,325,379.61 23,459.72 5. Mobilization 333,000.00 0.00 6. Total Work Completed 3,658,379.61 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,658,379.61 33,459.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,459.72