Dept. of Trans. PROGRESS Serial No. Contract No. 22-259-16-47 11-411504 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 4% Location: Federal Project: 11-SD-805-20.7/23.5 ACIM-805(642) Progress payment No. 002 Payment period ending: 09-20-22 MONTANO PIPELINE INC 231 FOURTH AVE CHULA VISTA CA 91910 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 286,691.66 278,291.66 2. a. Extra Work 70,886.21 70,886.21 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 357,577.87 349,177.87 5. Mobilization 260,000.00 260,000.00 6. Total Work Completed 617,577.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 617,577.87 609,177.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 609,177.87