Dept. of Trans. PROGRESS Serial No. Contract No. 22-144-08-47 11-4116U4 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 29% Location: Federal Project: 11-SD-8-13.4/R20.4 ACIM-008-1(328) Progress payment No. 005 Payment period ending: 05-20-22 PAL GENERAL ENGINEERING INC 2364 PASEO DE LAS AMERICAS #1 SAN DIEGO CA 92154 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 426,031.52 99,852.55 2. a. Extra Work b. Adustment Comp. 985.98 985.98 3. Materials on Hand 4. Earned Subject to Retention 427,017.50 100,838.53 5. Mobilization 86,250.00 28,750.00 6. Total Work Completed 513,267.50 7. Deductions -45,150.64 -32,088.13 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 468,116.86 97,500.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,500.40