Dept. of Trans. PROGRESS Serial No. Contract No. 23-230-22-55 11-412004 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 42% Location: Federal Project: 11-IMP-8-R32.4/R46.1 ACNH-X025(30) Progress payment No. 002 Payment period ending: 08-20-23 IBARRA GENERAL ENGINEERING INC 4325 TYROLITE ST RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 679,317.04 144,271.04 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 679,317.04 144,271.04 5. Mobilization 225,000.00 0.00 6. Total Work Completed 904,317.04 7. Deductions 0.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 904,317.04 147,271.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,271.04