Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 16-223-11-49 11-413304 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 37% Location: Federal Project: 11-SD-15-R6.5/R10.9 NHPI-015 4-207(E) Progress payment No. 005 Payment period ending: 07-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,099,140.06 194,313.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,099,140.06 194,313.00 5. Mobilization 778,053.83 259,351.28 6. Total Work Completed 1,877,193.89 7. Deductions -86,050.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,791,143.89 453,664.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 453,664.28