Dept. of Trans. PROGRESS Serial No. Contract No. 17-326-10-59 11-413304 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 99% Location: Federal Project: 11-SD-15-R6.5/R10.9 NHPI-015 4-207(E) Progress payment No. 021 Payment period ending: 11-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,098,359.09 120,914.24 2. a. Extra Work 584,674.42 92,413.24 b. Adustment Comp. -15,407.31 -67,576.82 3. Materials on Hand 4. Earned Subject to Retention 9,667,626.20 145,750.66 5. Mobilization 1,037,405.10 0.00 6. Total Work Completed 10,705,031.30 7. Deductions -3,000.00 13,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,702,031.30 158,750.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 158,750.66