Dept. of Trans. FINAL Serial No. Contract No. 18-157-15-11 11-413304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-15-R6.5/R10.9 NHPI-015 4-207(E) Progress payment No. 024 Payment period ending: 12-12-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,191,573.86 0.00 2. a. Extra Work 921,796.05 10,513.11 b. Adustment Comp. -15,407.31 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,097,962.60 10,513.11 5. Mobilization 1,037,405.10 0.00 6. Total Work Completed 11,135,367.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,135,367.70 10,513.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,513.11