Dept. of Trans. PROGRESS Serial No. Contract No. 16-112-17-30 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 12% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 003 Payment period ending: 04-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,584,263.51 2,267,069.89 2. a. Extra Work b. Adustment Comp. -93,664.73 -92,431.80 3. Materials on Hand 4. Earned Subject to Retention 7,490,598.78 2,174,638.09 5. Mobilization 3,754,646.81 0.00 6. Total Work Completed 11,245,245.59 7. Deductions -4,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,241,245.59 2,181,638.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,181,638.09