Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-13-58 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 17% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 004 Payment period ending: 05-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,391,533.58 2,807,270.07 2. a. Extra Work b. Adustment Comp. -107,148.39 -13,483.66 3. Materials on Hand 163,798.34 163,798.34 4. Earned Subject to Retention 10,448,183.53 2,957,584.75 5. Mobilization 4,755,885.96 1,001,239.15 6. Total Work Completed 15,040,271.15 7. Deductions -7,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,197,069.49 3,955,823.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,955,823.90