Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-11-48 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 21% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 005 Payment period ending: 06-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,590,070.02 8,198,536.44 2. a. Extra Work 8,734.79 8,734.79 b. Adustment Comp. -139,066.26 -31,917.87 3. Materials on Hand 133,698.65 -30,099.69 4. Earned Subject to Retention 18,593,437.20 8,145,253.67 5. Mobilization 4,755,885.96 0.00 6. Total Work Completed 23,215,624.51 7. Deductions -14,000.00 -7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,335,323.16 8,138,253.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,138,253.67