Dept. of Trans. PROGRESS Serial No. Contract No. 16-203-16-23 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 25% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 006 Payment period ending: 07-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,272,276.28 2,682,206.26 2. a. Extra Work 543,309.08 534,574.29 b. Adustment Comp. -139,672.67 -606.41 3. Materials on Hand 22,949.31 -110,749.34 4. Earned Subject to Retention 21,698,862.00 3,105,424.80 5. Mobilization 4,755,885.96 0.00 6. Total Work Completed 26,431,798.65 7. Deductions -17,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,437,747.96 3,102,424.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,102,424.80