Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-18-11 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 34% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 008 Payment period ending: 09-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,108,835.66 1,844,453.69 2. a. Extra Work 601,185.59 24,631.43 b. Adustment Comp. -140,807.48 -1,134.81 3. Materials on Hand 118,459.80 95,398.25 4. Earned Subject to Retention 24,687,673.57 1,963,348.56 5. Mobilization 4,755,885.96 0.00 6. Total Work Completed 29,325,099.73 7. Deductions -32,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,411,559.53 1,957,348.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,957,348.56