Dept. of Trans. PROGRESS Serial No. Contract No. 16-298-17-25 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 38% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 009 Payment period ending: 10-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,266,938.80 1,158,103.14 2. a. Extra Work 596,583.18 -4,602.41 b. Adustment Comp. -141,618.38 -810.90 3. Materials on Hand 136,678.29 18,218.49 4. Earned Subject to Retention 25,858,581.89 1,170,908.32 5. Mobilization 5,006,195.75 250,309.79 6. Total Work Completed 30,728,099.35 7. Deductions -20,000.00 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,844,777.64 1,433,218.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,433,218.11