Dept. of Trans. PROGRESS Serial No. Contract No. 16-358-08-04 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 46% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 011 Payment period ending: 12-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,546,347.82 9,513,701.78 2. a. Extra Work 609,165.52 2,708.66 b. Adustment Comp. -134,829.40 7,000.00 3. Materials on Hand 127,305.82 -327,526.69 4. Earned Subject to Retention 38,147,989.76 9,195,883.75 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 43,026,879.69 7. Deductions -30,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,124,185.51 9,190,883.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,190,883.75