Dept. of Trans. PROGRESS Serial No. Contract No. 17-023-14-50 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 50% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 012 Payment period ending: 01-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,340,298.09 3,793,950.27 2. a. Extra Work 1,067,095.42 457,929.90 b. Adustment Comp. -134,848.88 -19.48 3. Materials on Hand 0.00 -127,305.82 4. Earned Subject to Retention 42,272,544.63 4,124,554.87 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 47,278,740.38 7. Deductions -32,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,246,740.38 4,122,554.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,122,554.87