Dept. of Trans. PROGRESS Serial No. Contract No. 17-054-09-54 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 54% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 013 Payment period ending: 02-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,312,932.29 972,634.20 2. a. Extra Work 1,317,953.87 250,858.45 b. Adustment Comp. -137,407.12 -2,558.24 3. Materials on Hand 156,490.52 156,490.52 4. Earned Subject to Retention 43,649,969.56 1,377,424.93 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 48,499,674.79 7. Deductions -30,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,626,165.31 1,379,424.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,379,424.93