Dept. of Trans. PROGRESS Serial No. Contract No. 17-142-15-27 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 66% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 016 Payment period ending: 05-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,573,638.50 555,835.75 2. a. Extra Work 1,817,170.12 18,163.59 b. Adustment Comp. -189,800.40 0.00 3. Materials on Hand 0.00 -42,146.03 4. Earned Subject to Retention 46,201,008.22 531,853.31 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 51,207,203.97 7. Deductions -32,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,175,203.97 527,853.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 527,853.31