Dept. of Trans. PROGRESS Serial No. Contract No. 17-234-15-11 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 79% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 019 Payment period ending: 08-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,863,699.09 51,110.00 2. a. Extra Work 2,606,618.60 51,599.60 b. Adustment Comp. -183,448.89 142.27 3. Materials on Hand 4. Earned Subject to Retention 47,286,868.80 102,851.87 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 52,293,064.55 7. Deductions -45,986.25 -14,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,247,078.30 88,851.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 88,851.87