Dept. of Trans. PROGRESS Serial No. Contract No. 17-298-07-56 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 88% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 021 Payment period ending: 10-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,941,099.09 37,800.00 2. a. Extra Work 2,625,950.60 1,619.72 b. Adustment Comp. -183,448.89 0.00 3. Materials on Hand 4. Earned Subject to Retention 47,383,600.80 39,419.72 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 52,389,796.55 7. Deductions -50,986.25 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,338,810.30 31,419.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,419.72