Dept. of Trans. PROGRESS Serial No. Contract No. 17-331-18-14 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 92% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 022 Payment period ending: 11-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,000,159.09 59,060.00 2. a. Extra Work 3,003,355.57 377,404.97 b. Adustment Comp. -183,448.89 0.00 3. Materials on Hand 4. Earned Subject to Retention 47,820,065.77 436,464.97 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 52,826,261.52 7. Deductions -52,986.25 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,773,275.27 434,464.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 434,464.97