Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-005-16-42 11-413604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-IMP-8-R45.5/R55.0 NHPI-008(2) 105-E Progress payment No. 023 Payment period ending: 12-12-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,023,809.09 23,650.00 2. a. Extra Work 3,227,118.86 223,763.29 b. Adustment Comp. -70,153.77 113,295.12 3. Materials on Hand 4. Earned Subject to Retention 48,180,774.18 360,708.41 5. Mobilization 5,006,195.75 0.00 6. Total Work Completed 53,186,969.93 7. Deductions -67,986.25 -15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,118,983.68 345,708.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 345,708.41