Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-18-12 11-413704 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 24% Location: Federal Project: 11-IMP-8-R65.0/R74.5 NHPI-008-2(106) Progress payment No. 007 Payment period ending: 09-20-16 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,522,782.27 3,851,037.96 2. a. Extra Work 26,588.41 16,754.62 b. Adustment Comp. -3,994.82 -3,994.82 3. Materials on Hand 4. Earned Subject to Retention 9,545,375.86 3,863,797.76 5. Mobilization 4,559,043.35 959,798.60 6. Total Work Completed 14,104,419.21 7. Deductions -39,918.35 -7,298.60 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,064,500.86 4,816,297.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,816,297.76