Dept. of Trans. PROGRESS Serial No. Contract No. 17-023-14-55 11-413704 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 38% Location: Federal Project: 11-IMP-8-R65.0/R74.5 NHPI-008-2(106) Progress payment No. 011 Payment period ending: 01-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,980,460.41 6,142,367.13 2. a. Extra Work 1,381,278.94 151,347.19 b. Adustment Comp. -46,757.28 34,190.00 3. Materials on Hand 0.00 -32,323.45 4. Earned Subject to Retention 30,314,982.07 6,295,580.87 5. Mobilization 4,798,993.00 0.00 6. Total Work Completed 35,113,975.07 7. Deductions -35,493.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 35,078,482.07 6,296,580.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,296,580.87