Dept. of Trans. PROGRESS Serial No. Contract No. 17-115-15-07 11-413704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 48% Location: Federal Project: 11-IMP-8-R65.0/R74.5 NHPI-008-2(106) Progress payment No. 014 Payment period ending: 04-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,649,897.44 3,637,130.64 2. a. Extra Work 1,796,174.42 149,239.90 b. Adustment Comp. -17,782.96 28,974.32 3. Materials on Hand 5,257.64 -9,248.43 4. Earned Subject to Retention 42,433,546.54 3,806,096.43 5. Mobilization 4,798,993.00 0.00 6. Total Work Completed 47,227,281.90 7. Deductions -34,493.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,198,046.54 3,811,096.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,811,096.43