Dept. of Trans. PROGRESS Serial No. Contract No. 17-142-15-34 11-413704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 52% Location: Federal Project: 11-IMP-8-R65.0/R74.5 NHPI-008-2(106) Progress payment No. 015 Payment period ending: 05-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,912,399.87 262,502.42 2. a. Extra Work 1,843,586.38 47,411.96 b. Adustment Comp. -17,654.91 128.05 3. Materials on Hand 0.00 -5,257.64 4. Earned Subject to Retention 42,738,331.34 304,784.79 5. Mobilization 4,798,993.00 0.00 6. Total Work Completed 47,537,324.34 7. Deductions -41,493.00 -7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,495,831.34 297,784.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,784.79