Dept. of Trans. PROGRESS Serial No. Contract No. 17-298-07-54 11-413704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 70% Location: Federal Project: 11-IMP-8-R65.0/R74.5 NHPI-008-2(106) Progress payment No. 020 Payment period ending: 10-20-17 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,229,724.43 95,134.57 2. a. Extra Work 2,723,895.78 60,001.78 b. Adustment Comp. -77,374.26 21.48 3. Materials on Hand 4. Earned Subject to Retention 44,876,245.95 155,157.83 5. Mobilization 4,798,993.00 0.00 6. Total Work Completed 49,675,238.95 7. Deductions -46,493.00 -9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,628,745.95 146,157.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 146,157.83