Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-14-51 11-414304 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 53% Location: Federal Project: 11-SD-79-34.2/36.5 ACST-P079(42) Progress payment No. 003 Payment period ending: 06-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 227,979.70 59,056.25 2. a. Extra Work 766.03 766.03 b. Adustment Comp. 3. Materials on Hand 0.00 -9,454.60 4. Earned Subject to Retention 228,745.73 50,367.68 5. Mobilization 101,250.00 0.00 6. Total Work Completed 329,995.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 329,995.73 50,367.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,367.68