Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-14-36 11-414304 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 100% Location: Federal Project: 11-SD-79-34.2/36.5 ACST-P079(42) Progress payment No. 007 Payment period ending: 11-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,671.60 29,513.90 2. a. Extra Work 21,553.54 817.50 b. Adustment Comp. 3. Materials on Hand 13,261.44 0.00 4. Earned Subject to Retention 528,486.58 30,331.40 5. Mobilization 128,250.00 0.00 6. Total Work Completed 643,475.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -3,033.14 -3,033.14 c. Reduction after 95% Comp. 9. Total pay to Contractor 653,703.44 27,298.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,298.26